Week ending 20.03.26

  • Mar 20
  • 1 min read

Works are progressing well on site. Underpinning is in good flow with circa 12 pins constructed. The steelwork is due to commence manufacture and should be on site being installed on site in circa 3 weeks time. The chimneys are currently being removed internally following the install of temporary support works.

 
 

Recent Posts

See All
Week ending 20/02/26

Works are progressing well on site with the 4 lead baes and underpins constructed and being concrete poured next week. These are the key bases for the steel wind posts that run up both sides of the bu

 
 
Week ending 06/02/26

Structural works have now begun on site with the super structure team now on site. Activities planned for the next 2 weeks include formation of pins, further demo, scaffold gantry for the conveyor and

 
 
Week ending 16/01/26

We are currently stripping walls of plaster/render. This will allow datums to be set onto the walls for setting out datums. Also prepares the walls for the temp props and whalers. The formation of tri

 
 