Week ending 20.03.26
- Mar 20
- 1 min read
Works are progressing well on site. Underpinning is in good flow with circa 12 pins constructed. The steelwork is due to commence manufacture and should be on site being installed on site in circa 3 weeks time. The chimneys are currently being removed internally following the install of temporary support works.

