Week ending 06/02/26
- Feb 6
- 1 min read
Updated: Mar 11
Structural works have now begun on site with the super structure team now on site. Activities planned for the next 2 weeks include formation of pins, further demo, scaffold gantry for the conveyor and lowering levels to the lower ground floor with removal of slab and earth. Once the gantry is complete we will complete our hoarding around the gantry with screen printed logo boards.