Works planned for next week

Ply deck to the roof steels

Formation of the box gutter to 3rd

Formation of roof light upstands

Brickwork repairs

Installing partitions to 2nd floor

Installing joists to 1st floor steel

Continuation of under pinning to basement and vaults


Partitions to 3rd floor are built and are also underway on 2nd floor

Joisting of 1st floor will begin from next week

Underpinning continues within the basement

Vault works continue


Our roof level is being prepared for finishes due to commence shortly. 3rd floor partitions have commenced as have 2nd floor and we will shortly be commencing our MEP works to these levels.

1st floor steel work has commenced and we continue with 2nd stage underpinning to the basement. To the front we are forming the new vaulted are and lightwell.