Week ending 20/02/26

  • Feb 20
  • 1 min read

Updated: Mar 11

Works are progressing well on site with the 4 lead baes and underpins constructed and being concrete poured next week. These are the key bases for the steel wind posts that run up both sides of the building and are the key supports for the steel frame to be installed.

Our gantry to the road with conveyor will shortly be completed and then clad with screen printed design panels. We have had our first 3 grab lorries attend and remove the spoil from site.

 
 

Recent Posts

See All
Week ending 20.03.26

Works are progressing well on site. Underpinning is in good flow with circa 12 pins constructed. The steelwork is due to commence manufacture and should be on site being installed on site in circa 3 w

 
 
Week ending 06/02/26

Structural works have now begun on site with the super structure team now on site. Activities planned for the next 2 weeks include formation of pins, further demo, scaffold gantry for the conveyor and

 
 
Week ending 16/01/26

We are currently stripping walls of plaster/render. This will allow datums to be set onto the walls for setting out datums. Also prepares the walls for the temp props and whalers. The formation of tri

 
 