Week ending 20/02/26
- Feb 20
- 1 min read
Updated: Mar 11
Works are progressing well on site with the 4 lead baes and underpins constructed and being concrete poured next week. These are the key bases for the steel wind posts that run up both sides of the building and are the key supports for the steel frame to be installed.
Our gantry to the road with conveyor will shortly be completed and then clad with screen printed design panels. We have had our first 3 grab lorries attend and remove the spoil from site.