Week ending 22.05.26
- May 21
- 1 min read
Our scaffold is 80% erected and is on track to be complete by close of next week. Underpinning to the 1st stage is complete internally and steelwork continues up through the building. The completion of the scaffold due end of next week, releases much further works internally and externally to the vault and lightwell.