Week ending 1st May 2026

  • May 1
  • 1 min read

30 pins are now constructed at their first stage and steelwork is being installed through the building. We will be commencing the scaffolding to the property within the next 2 weeks which kick starts the remaining roof demolition and floors internally. This also allows the new floor constructions to start.

 
 

Recent Posts

See All
Week commencing 1st June

Our scaffold will be complete this week allowing full access all around the building. Our rear steel box frame is also being installed along with temporary steel work support to the front bay. Once th

 
 
Week ending 22.05.26

Our scaffold is 80% erected and is on track to be complete by close of next week. Underpinning to the 1st stage is complete internally and steelwork continues up through the building. The completion o

 
 
Week ending 8th May 2026

Scaffold preparation has been implemented to enable the install to commence Monday 11th. Forming of 1st stage underpinning is drawing to an end with 2 left internally. Steelwork is continuing and some

 
 