Week ending 14/11/25

  • edmundlehmann
  • Nov 14, 2025
  • 1 min read

Our internal strip out works are progressing well with 2 floors cleared of fixtures and fittings back to bear stud walls and joisted ceilings.

 

To the rear garden our site cabin is also progressing well, which will house our Project/Site management team, a canteen/WC and meeting room as well as a very well much needed drying room when our staff need to dry their clothes overnight.

 

Lastly, we have had several meetings this week with our security engineers, structural engineers, scaffolders and MEP contractors on site.

 

We hope to have another floor cleared by close next Friday 21st November.

 
 

Recent Posts

See All
Week endin g 12.12.25

We have now cleared floors 3rd to ground floor and commence the final level in the next day - namely the lower ground floor strip out. The front hoarding has commenced also now and we are on track to

 
 
Week ending 21.11.25

Works are progressing well with the strip out achieving a further level completed by the close of the week. The site cabin to the rear garden is also complete now. We anticipate being complete around

 
 
Neighbour Letter

3 rd November 2025 Dear Homeowner / Occupier,                                                               Ref 13 Belsize Crescent NW3 Construction project   We are writing to advise you that we have

 
 