Week commencing 5.10.26

Oct 2
1 min read

Partitions to 3rd floor are built and are also underway on 2nd floor

Joisting of 1st floor will begin from next week

Underpinning continues within the basement

Vault works continue


 
 

Recent Posts

See All
Week commencing 19.10.26

Works planned for next week Ply deck to the roof steels Formation of the box gutter to 3rd Formation of roof light upstands Brickwork repairs Installing partitions to 2nd floor Installing joists to 1s

 
 
Week commencing 21st September

Our roof level is being prepared for finishes due to commence shortly. 3rd floor partitions have commenced as have 2nd floor and we will shortly be commencing our MEP works to these levels. 1st floor

 
 
Works commencing 24th August 2026

Our works are progressing well. Next week we will be carrying out; Continuation of roof joisting Installing rebar into the rib deck and pouring the concrete Continuation of 2nd floor joisting Continua

 
 