Week commencing 19.10.26

1 day ago
1 min read

Works planned for next week

Ply deck to the roof steels

Formation of the box gutter to 3rd

Formation of roof light upstands

Brickwork repairs

Installing partitions to 2nd floor

Installing joists to 1st floor steel

Continuation of under pinning to basement and vaults


 
 

Recent Posts

See All
Week commencing 5.10.26

Partitions to 3rd floor are built and are also underway on 2nd floor Joisting of 1st floor will begin from next week Underpinning continues within the basement Vault works continue

 
 
Week commencing 21st September

Our roof level is being prepared for finishes due to commence shortly. 3rd floor partitions have commenced as have 2nd floor and we will shortly be commencing our MEP works to these levels. 1st floor

 
 
Works commencing 24th August 2026

Our works are progressing well. Next week we will be carrying out; Continuation of roof joisting Installing rebar into the rib deck and pouring the concrete Continuation of 2nd floor joisting Continua

 
 