Week commencing 3rd August 2026
- Jul 31
- 1 min read
We continue with our roof steel installation which is planned to complete by the end of this week. Along with this some 2nd floor steel installation will start and our 1st floor steel will be delivered to site.
The front lightwell continues to be underpinned for all of next week also while we prepare to start our 2nd stage underpinning internally.